The project sponsor requests that an element of a product will be swapped for the equivalent supplied by a local manufacturer. In order to have a more sustainable supply chain. 

Which action should the project manager take? 

A project is at the planning stage. The project manager realizes that producing a complex, multi-functional application is NOT feasible with the current number of resources and decides to hire more resources for the production of the application. The project manager identifies and contracts temporary resources. 

Which risk response strategy does this scenario exemplify? 

Two (2) users complain during the project's user acceptance stage, saying that their expectations were NOT met. 

What could the project manager use to avoid this issue in the future? 

A project is 7 months into execution. The project manager determines that the cost performance index (CPI) is 0.80. 
According to trend analysis, the CPI has a downward trend. 

What should the project manager do next? 

A company wants to reduce future operating costs by installing solar panels on the facility being built by using a local government subsidy for energy-efficient projects. They have NOT yet applied for the subsidy. 

Before the project starts, the project manager is describing reject risks.

Which statement best describes the risk to the project if the application is NOT successful?  

A project has the following characteristics: 

• A quality management plan Is in place. 
• The quality management plan states that project deliverables must be reviewed, at a minimum, 15 weeks before the deadline. 

• Four (4) deliverables have missed this quality requirement. 

Which step should the project manager take? 

Two start-up companies have merged, and now more than 100 developers on eight (8) agile teams are working on a common portfolio. 

Which agile practice or method can best ensure release coordination between the teams? 

A key stakeholder voices a concern during the planning stage about whether the available resources are adequate to meet the objectives of the project. After further discussion about the requirements and the number of resources Identified, the project manager is hesitant about the original plan. 

Which two steps should the project manager take next? (Choose TWO)

A project is in the execution stage. Based on the originally approved blueprint, 1,000 products were developed. The project team randomly chooses 100 products to evaluate against the quality plan. 

What is the project team undertaking? 

Review the following steps 
1 A project has been successfully delivered. 
2 The project manager is executing formal closure 
3  ______________________________________

What is Step 3? 

The project sponsor requires a project team composed of resources that live in four different time zones, working in four different locations. The project sponsor did NOT consider the challenges created by this requirement and believes that the dispersion will provide an ideal project team that will save costs.

Where should the project manager document this in the project charter? 

After a project ends, the project manager and project team members are still being asked to do the following: 

• Evaluate new requirements 

• Make minor modifications 

• Solve technical issues 

The project manager wants to ensure the product or service developed by the project now has operational support. 

What should the project manager do? 

A project manager in an organization that uses traditional project management is assigned to an ongoing project. Recently, the organization has started to use agile methodologies for projects. The project manager hears that some team members think key subject matter expertise is missing and that the team does NOT collaborate enough. 

How should the project manager respond to these team members' concerns? 

Because a deliverable does NOT meet the agreed-upon quality specifications, it is rejected by the customer. Team members find that the deliverable fails to meet expectations because of a problem with vendor-provided parts.
The vendor says that they will NOT correct the problem 

Before deciding on the next steps, what should the project manager do? 

A company is losing market share to disruptive competitors with new business models. A cross-functional agile team has been formed to recommend ways to recover market share.

How can the team increase their chance of producing successful recommendations? 

A project manager receives complaints from a project sponsor because of a delay in developing a prototype.

The project manager consults the resource management plan and responds that the delay was due to a bolt of knowledge in a specific skill at was needed by the cross-notional project team. 

How can the project manager perform this task better in the future?

A project manager is preparing the charter for a project.The project aims to automate 30 percent of product testing. The project sponsor advises the project manager to assign senior test engineers to identify the tests that can be automated. The test department manager, however, is NOT cooperative because they believe that the project will lead to downsizing in their department 

Which two actions are suitable in this scenario? (Choose TWO.) 

A company is struggling to define the scope of a new project that has multiple phases with a high level of dependency between the phases. 

How should the project manager approach this challenge? 

While a project manager is preparing the monthly project status report, four (4) new risks are identified. These four (4) risks could affect key milestones. 

What should the project manager do before presenting this new risk information? 

An agile innovation team is highly productive. However, the Head of Operations informs the product owner that the company is NOT getting sustainable return on investment from the team's work. 

How should the product owner address the problem? 