1. A construction company has entered into a contract with a local school district to build a new school. The contract, following AIA Document A101-2017, specifies a 12-month period for completion, with the clause that if the project is not substantially completed within this timeframe, the construction company will owe the school district liquidated damages of $1,000 per day. The project unfortunately runs into delays due to the construction company's management issues, and the completion extends two months beyond the scheduled timeframe. How would the liquidated damages clause apply in this situation?

Save
Next Page »
Answered 0 of 20 (0%)
Bookmarks: